Edinburgh Gateway Project
Traffic management timeline during construction of the new Gogar train station and A8 underpass.
Anticipated start date Wednesday 13th May: duration up to 40 weeks
- Phase 1 – city bound lane restrictions on the off-slip from Gogar roundabout towards Maybury. Expected duration 5 days
- Phase 2 citybound Gogar underpass closed overnight, diversion signposted around the roundabout. Expected dates 21st – 23rd and 25th – 26th May
- Phases 3, 4 and 5 – lane closures and contraflow on the east side of Gogar junction.
Expected duration 10 weeks per phase
Further information
This work forms part of the Edinburgh Glasgow Improvement Programme – www.egip.info
and www.twitter.com/networkrailEGIP